On 06.01. Zemis d.o.o. successfully participated in the emergency intervention on the repair of the leak of the buried gas pipeline DN450 with a working pressure 6 bar connecting MRS Sisak and TE-TO Sisak. Due to the impossibility of interrupting the operation of the gas pipeline due to the supply of the TE-TO Sisak plant, the repair had to be done online, and for that purpose 3X Engineering Stopkit® 100 was used – a special Emergency Pipeline Repair System for online leak sealing.
Thanks to the quick intervention, the repair was carried out in the shortest possible time, and the security of supply of TE-TO Sisak with natural gas was ensured.